The Situation:
Manufacturing & Warehouse- CEVA
Key Features:
2,400kW Parallel Diesel System
- 2 Building Feeds 1,200kW Each
- 3 x Generac MD400 rated at 400kW each for both Building Feeds
- Level 1 Sound Enclosure
- 3000A Collection Panelboard w/ built in SE Rated ATS
- MPS System offered
- Critical load redundancy
- Reduced lead time
- 2,400kW / 480V
The Solution:
CEVA, one of the largest supply chain management companies in the world, needed a standby power solution for a large distribution center in Mt. Juliet, TN. We were able to help them size up a parallel solution on both of the two building feeds that covers the complete loads under normal circumstances and offers critical load redundancy. An added bonus was that we were able to reduce the lead time for the generator package utilizing smaller nodes which are much more readily available. Because our MPS system does not require switchgear for parallel operation the commissioning is just as simple as a single set installation.