Not only are these our elders who are in need of love and care, they are veterans! So we were doubly happy to help. We specialize in healthcare, and this is becoming a more and more important type of care each year.
This project presented a key challenge in that they wanted to use natural gas at this Veterans Administration Retirement Home but also wanted to have onsite fuel.
To accomplish this, we used our 150kW node which provides the best NG/LPG performance in our MPS (Modular Power System) System. The loads were separated in multiple ATS’s allowing us to meet NFPA requirements for life safety as well as critical loads. The onboard paralleling does not require any expensive and complex switchgear so this solution came together without hurting the budget, lead times, commissioning schedule or the application.
A 5 x 150kW package may seem like an unusual combination for a 750kW generator system, but sometimes customer requirements lead to creative solutions.
Key Features:
750kW Parallel, Dual Fuel System
- 5 x Generac MG150 rated at 150kW each
- Level 1 Sound Enclosure
- PM-SC System Controller
- 750kW / 480V
- On-site LPG Fuel Tank
- Expandable for future growth
- Common power node for simplified maintenance and service